Enbridge Gas applies a cutoff date of September 1 for service applications to be considered for installation within the same construction season. Applications submitted on or before this date are eligible to be scheduled and completed within the current calendar year.
Requests received after September 1 are handled on a best-efforts basis only. As a result, installation cannot be guaranteed within the same calendar year, as scheduling depends on remaining capacity and external constraints.
This cutoff date was established to allow sufficient time to properly review, process, and coordinate each service request. Adequate lead time is necessary to ensure safe and efficient project planning.
In addition, increased requirements from external stakeholders – such as permitting approvals and road cut restrictions – often necessitate extended installation timelines. These factors can further impact scheduling and completion dates, even when applications are submitted before the cutoff.