The Town of Whitby has opened their second consultation phase and released more background information on their review.
The second phase of consultation opened on December 1 and will be closing on January 8, 2021. This consultation period will cover the information included in staff report CS 50-20, including the draft capital forecast and draft rates. This report also includes DRHBA's initial submission and the Town's response.
Proposed Timeline:
- February 11, 2021 - Development Charge Background Study completed
- March 8, 2021 - Statutory public meeting
- April 12, 2021 - Bylaw brought to council
- May 1, 2021 - New rates become effective
It should be noted that Whitby's current development charge bylaw does not expire until March 24, 2022. As the Town is updating their bylaw one year early, DRHBA has asked for the timelines to be extended to allow for more fulsome discussion.
A snapshot of the proposed increase: